Setting Group Failover Order
VM groups in a failover plan are processed in the order they appear in the Plan Groups list. If some VMs in a group are dependent upon VMs in other groups, make sure that the required group is failed-over first.
To change the processing order for groups included into a failover plan:
- Select the plan and click Manage > Edit.
- On the Edit Plan page:
- In the Plan Groups column, select a group.
- To move the group up or down the list, use the Up and Down arrows.
- To save changes made to the plan settings, click Save.
|
By design, failover plans contain two default groups — Pre-failover steps and Post-failover steps. These groups include plan steps that run before and after the failover process. You cannot change the processing order for the Pre-failover steps and Post-failover steps groups, but you can add and remove steps for these groups. For more information, see Overriding VM Recovery and Protection Settings. |