Running and Scheduling Replica Plans

To run a replica plan, it must be ENABLED. To enable a plan:

  1. Navigate to Recovery Plans.
  2. Select the plan.
  3. From the Manage menu, select Enable.

-OR-

Right-click the plan name and select Manage > Enable.

 

If you do not enable a plan before you run it, the Run Plan wizard will force you to do that as soon as you try running the plan.

Notes

  1. An Orchestrator Administrator or Plan Operator can force-enable a plan in the Run Plan wizard. However, a Plan Operator will not be able to run a disabled replica plan.

For more information on roles that can be assigned to users and user groups working with the Orchestrator UI, see Managing Scopes.

  1. For security purposes, all ‘real-world’ actions associated with replica plans (such as failover and failback) require password confirmation.

In This Section